Earthworks
Flooring (machine) [m2] | Vase and Nuno-bori, depth: about 2.5m (Incl. Labor costs and Expenses)
11千葉市住宅供給公社_限度額表(R02)
つぼ・布堀 深さ2.5m程度(手間のみ、経費とも)
¥381
Skimming (machine) [m3] | both in terms of time and money
11千葉市住宅供給公社_限度額表(R02)
手間のみ、経費とも
¥563
Disposal of residual soil (machine) [m3] | Leveling of the site (Incl. Labor costs and Expenses)
11千葉市住宅供給公社_限度額表(R02)
場内敷き均し(手間のみ、経費とも)
¥611
Disposal of residual soil (human power) [m3] | Leveling of the site (Incl. Labor costs and Expenses)
11千葉市住宅供給公社_限度額表(R02)
場内敷き均し(手間のみ、経費とも)
¥891
Root cutting (machine) [m3] | Vase, Nuno-bori, depth of about 2.5m (Incl. Labor costs and Expenses)
11千葉市住宅供給公社_限度額表(R02)
つぼ・布堀 深さ2.5m程度(手間のみ、経費とも)
¥990
Backfilling (machine) [m3] | both time and money
11千葉市住宅供給公社_限度額表(R02)
手間のみ、経費とも
¥1,380
Tree removal and relocation [pcs] | less than 50cm in height (root roll, temporary support, trunk roll) (Incl. Labor costs and E
11千葉市住宅供給公社_限度額表(R02)
樹高50cm未満 根巻き・仮支柱・幹巻き別途(手間のみ、経費とも)
¥1,400
Tree extraction [pcs] | less than 50 cm in height Disposal costs (both labor and disposal, Expensess)
11千葉市住宅供給公社_限度額表(R02)
樹高50cm未満 処分費共(手間・処分のみ、経費とも)
¥1,810
Felling of trees [pcs] | Trunk circumference less than 30cm Cost of disposal (labor and disposal only, with Expensess)
11千葉市住宅供給公社_限度額表(R02)
幹周30cm未満 処分費共(手間・処分のみ、経費とも)
¥1,830
Tree removal and relocation [pcs] | Tree height more than 50cm but less than 100cm Root winding, temporary support, and trunk w
11千葉市住宅供給公社_限度額表(R02)
樹高50cm以上100cm未満 根巻き・仮支柱・幹巻き別途(手間のみ、経費とも)
¥2,100
Tree extraction [pcs] | Tree height more than 50 cm but less than 100 cm Disposal cost (labor and disposal only, both costs)
11千葉市住宅供給公社_限度額表(R02)
樹高50cm以上100cm未満 処分費共(手間・処分のみ、経費とも)
¥4,450
Tree removal and relocation [pcs] | Tree height more than 100cm but less than 200cm Root winding, temporary support, and trunk
11千葉市住宅供給公社_限度額表(R02)
樹高100cm以上200cm未満 根巻き・仮支柱・幹巻き別途(手間のみ、経費とも)
¥4,780
Felling of trees [pcs] | Trunk circumference 30cm or more but less than 60cm Cost of disposal (labor and disposal only, both ex
11千葉市住宅供給公社_限度額表(R02)
幹周30cm以上60cm未満 処分費共(手間・処分のみ、経費とも)
¥4,890
Conveyance of residual soil (machine) [m3] | Loading and unloading (Incl. Labor costs and Expenses)
11千葉市住宅供給公社_限度額表(R02)
積込み共(手間のみ、経費とも)
¥5,920
Backfilling (human-powered) [m3] | both in terms of time and money
11千葉市住宅供給公社_限度額表(R02)
手間のみ、経費とも
¥8,710
Felling of trees [pcs] | Trunk circumference 60cm or more but less than 90cm Cost of disposal (labor and disposal only, both ex
11千葉市住宅供給公社_限度額表(R02)
幹周60cm以上90cm未満 処分費共(手間・処分のみ、経費とも)
¥10,700
Tree extraction [pcs] | Tree height 100cm or more but less than 200cm Disposal cost (labor and disposal only, both costs)
11千葉市住宅供給公社_限度額表(R02)
樹高100cm以上200cm未満 処分費共(手間・処分のみ、経費とも)
¥14,500
Root cutting (human power) [m3] | only time and money
11千葉市住宅供給公社_限度額表(R02)
手間のみ、経費とも
¥14,700
Felling of trees [pcs] | Trunk circumference 90cm or more but less than 120cm Cost of disposal (labor and disposal only, both e
11千葉市住宅供給公社_限度額表(R02)
幹周90cm以上120cm未満 処分費共(手間・処分のみ、経費とも)
¥20,300
Machine transportation [round trip] | transportation by a large trailer with a backhoe of 0.5 or more (Incl. Labor costs and Exp
11千葉市住宅供給公社_限度額表(R02)
バックホウ0.5以上で大型トレーラーによる回送(手間のみ、経費とも)
¥48,700